Bay-Adelaide Centre West
Toronto, ON

Bay-Adelaide Centre West

The Bay-Adelaide Centre West (Phase 1) Tower in Toronto was the first steel-framed, high-rise building to be constructed in Toronto in over 10 years and the only LEED certified Core and Shell Gold office building. The building is designed as a landmark signature tower, with a distinctive rooftop silhouette that leaves an architectural imprint on the skyline. Standing at 52 storeys, this AAA building is home to some of Canada’s top-tier companies including Thomson Reuters.

Status
Completed
Client
EllisDon
Owner
Brookfield Properties
Architect
WZMH Architects
Structural engineer
Halcrow Yolles
Construction manager
EllisDon Construction
LEED Certification
Facts & Figures
  • Erection started in late 2007 and was completed in a tight timeframe of eleven months
  • 715 feet tall
  • New building was interfaced with the historical façade
Our Role

Walters was responsible for the detailing, fabrication, and erection of the 52 floors of structural steel framing. We supplied connection/construction engineering, detailing, fabrication, and erection of 9,500 tons of structural steel, the metal deck, and supplied crane and operation.

Overcoming Challenges

The design of the building integrates the 11-storey historic façade of the former National Building.  Interfacing the steel with the historical façade was delicate work.

Working within a tight footprint was also a challenge.  We developed and built our own crane climbing system to work within the site logistics and to meet the tight schedule.

ARCHITECTS
Integration and marriage of the reconstructed façade of the original heritage building with the new modern, clean look makes for a visually intriguing building. The architect used a corner detail framing design utilizing cantilevered construction to allow for eight prestigious corner offices on each floor.

Structural Engineers
The large loads at the level ten, sloping column transfers, were a challenge to design and build into reality.

General Contractors
To meet the aggressive schedule of the project, we had to work closely with the concrete contractor to coordinate the pouring of concrete core ahead of steel erection so that we could work simultaneously.

We also had to manage a major design change mid-project that involved relocating the mechanical level which resulted in creating an additional floor.

Location
333 Bay Street, Toronto, Ontario M5H 2R2, Canada
Awards
CISC 2010 Award for Engineering
Award of Merit
Project News
Project Inquiry
We’d be happy to brainstorm with you, answer any questions, or review the drawings for your upcoming project.
Related Projects