Toronto, September 12th – Walters Group continues to make significant progress at the ONE Tower in downtown Toronto with the successful installation of corner braces spanning floors 59 to 65. The Walters Field Services team ensured the site was prepared for the arrival of steel shipments at 3 PM, completing erection by 9:15 PM.
The crew worked diligently to secure all corner braces, seamlessly building upon the progress achieved in June, when corner braces were successfully installed between floors 51 and 57.
Learn more: www.waltersgroupinc.com/walters-group-installs-corner-braces-at-the-one/
Walters Group is proud to be contributing to this landmark project, reshaping Toronto’s skyline.
Special thank you to everyone involved in making this project possible.
Learn more about our role at the ONE Tower: www.waltersgroupinc.com/project/the-one-tower/