A 6,000-seat arena that serves as a major venue for sports and entertainment in St. Catharines, Ontario.
Walters Group supplied all the structural steel and designed the roof steel. The size of the project required the fabrication services of all three Walters plants (Hamilton, Princeton and Stoney Creek). Walters Field Services performed the installation.
Our largest challenge was meeting an inflexible 10-week erection schedule (starting in August 2013). We used two cranes to meet the deadlines: An 80-ton crane for the outer bowl and a 160-ton crane for the inside bleachers and roof steel. We also planned ahead, ensuring a sufficient backlog of fabricated structural steel prior to starting erection to allow our expert field crew to establish and maintain on-site continuity and satisfy the project schedule requirements.