Algoma Steel EAF Melt Shop Building
Sault Ste. Marie, ON

Algoma Steel EAF Melt Shop Building

Algoma Steel Inc. is constructing two state-of-the-art electric-arc-furnaces (EAF) to replace the existing blast furnace and basic oxygen steelmaking operations. The transformation is expected to reduce Algoma’s carbon emissions by approximately 70%, making the project among Canada’s largest GHG reduction efforts.

Algoma Steel worked with Danieli and JNE Engineering on the new Electric Arc Furnace at Algoma’s flagship plant in Sault Ste. Marie, Ontario.

Walters is using Algoma’s steel plate products to fabricate the heavy structural components and work with the local industrial contractor, SIS Manufacturing Inc., to fabricate key elements. The onsite assembly of the building structure commenced in the fall of 2022.

Status
In-Progress
Client
Algoma Steel Inc
Owner
Algoma Steel Inc
Partner(s)
SIS Manufacturing Inc., Burnco, and Nucor Vulcraft (suppling joists)
Structural engineer
JNE Consulting Ltd.
Facts & Figures
  • 15,000 Ton project
  • The main building is almost 1,000 ft long and 180 ft tall
  • 40 ft dust hood modules
Our Role

Walters is providing the detailing, supply and installation of structural steel, heavy crane girders, stick steel and plate modules. Additionally, Walters is responsible for all the connection engineering on the project.

Walters has now successfully completed the erection of the main Algoma Steel Electric Arch Furnace building, signifying a pivotal phase in the project’s evolution.

Now, Walters Group has installed 27 impressive 40ft tall dust hood modules, erected atop the towering 180ft building using a 660-ton crane for final placement. Leveraging modular construction methods, we maximized safety, operational efficiency, and facilitated substantial cost savings.

This approach reflects our unwavering commitment to delivering projects on time and optimizing resources.

Overcoming Challenges

The EAF dust hood above the furnaces will exhaust all smoke and heat through an intricate duct system to the scrubbers to minimize environmental impacts. The dust hood design and installation was a challenge, given the weights of approximately 1500 tons and the need for a 660-ton crane for final placement.

Location
105 West Street Sault Ste. Marie, Ontario, Canada
Project News
Project Inquiry
We’d be happy to brainstorm with you, answer any questions, or review the drawings for your upcoming project.